Dec
07New Restaurant Taking Shape
Filed Under (Construction of a New Restaurant, Menu Development, Planning a Restaurant, Restaurant Equipment and Supplies) by Larry on 07-12-2008
Tagged Under : equipment, smallwares, supplies
This past week or more has been a whirlwind of progress (finally). Here is a list of achievements;
- With the exception of the fan on the roof, the hood is in. It passed inspection and the fireproof duct work is completed.
- The fireproof tenant separation ceiling is up, taped and “mudded”. Waiting for inspection tomorrow, Monday, December 8, 2008.
- The electrical circuits are run and passed the rough-in inspection. The wall electrical inspection, which allows us to close all walls, should be inspected Monday.
- All walls are drywalled on one side and waiting for the electrical inspection to cover other side.
- As of last night a crew was completing some floor tile work in customer visible areas.
The items above may not seem like a big move forward, but you must consider we are dealing with 1800 square feet of space. That means when the restaurant contractors put the ceilings, tile and electrical into the location, the contractors are covering front to back.
This week should complete 90% of the rough-in construction. We have a schedule that looks like this:
- Monday - get electrical inspection. Begin covering rest of walls. Starting ceiling grid for drop-in ceiling tiles. Get final inspection on fireproofed ceiling separation. Order and construction of all counter tops.
- Tuesday - Complete wall covering and drywall mudding and taping after screw inspection. Complete drop-in ceiling. Install data wiring for POS system, phone and cable.
- Wednesday - Finish office space to begin putting up shelving, work space and computer locations. Start kitchen and bathroom floor tile. Grid system for ceiling complete for electrician to begin installing lighting.
- Thursday - Complete office and storeroom. Finish all flooring. Finish all electrical. Do wall finishing with primer and “knockdown” coat. Install FRP in kitchen. Plumber to starting final connections including gas piping. Wi-fi system in office.
- Friday - Paint walls final teal color and install wood beadboard. Start scheduling delivery of restaurant booths and equipment for following week.
- Saturday - Install baseboard. All counters installed. Office completed and operating with filing shelving and accounting computer. Start decorative shelving and finish work for interior.
- Sunday - Have restaurant cleaning crew come in and do complete cleaning before booths and equipment start arriving following week. Install video security system.
While all of the above work deals primarily with construction, during the coming week we will also;
- Order all remaining restaurant equipment to be purchased by Wednesday. Remember we have already purchased a lot of the kitchen equipment as we found bargains.
- Place a smallwares order for delivery early the following week.
- Purchase stainless shelving and install Friday or Saturday in kitchen.
- Schedule delivery and setup of POS system, beverage machines and cleaning system installation.
- Complete menu and testing. Start working on inventory initial order.
- Start interviewing potential employees late in the week. Process to continue until open.
- Complete forms and all filing and background office system.
If we have any chance to open before year end, next week will be the determining factor.


