13A Little Luck - Permits for Restaurant Issued
Filed Under (Construction of a New Restaurant, Planning a Restaurant, Restaurant Equipment and Supplies) by Larry on 13-11-2008
Tagged Under : construction, delay, permits, plan
If you have followed the blog, you know we have been slowed to a creeping halt by the county while waiting on the restaurant construction permits to be issued. Our last hang-up was with a plan reviewer who was relatively new on the job, but had undertaken his bureaucratic responsibilities a little too seriously when he started to “interpret” the codes rather than just enforce the codes. This has been a five and a half week battle.
In any event, there was a meeting scheculed with the architect and general contractor with the mechanical plan reviewer for yesterday morning. The reviewer didn’t show up. Both the architect and contractor were livid and apparently expressed themselves loud enough for the Director of the department to overhear. The Director took it upon himself to disappear with the plans for about twenty minutes and reappear with them fully approved! All the items that the architect and contracter were there to argue were OK’d!
Luck or perseverance won the battle - we are not sure which. Construction in earnest started yesterday afternoon. In the next post pictures will be posted to show progress as we go along.
This morning the contractor and I will be developing a schedule to make sure all the sub-contractors, suppliers and tradesmen know we must make up time on this project. It will be a seven day a week plan.